TRILITY, as part of the Helena Water consortium has been awarded the contract for the financing, design, build and operation of the 165 ML/d Mundaring Water Treatment Plant and Mundaring Pump Station C in Western Australia.

Snapshot

Project Name Mundaring Water Treatment Plant
Client Water Corporation
Type of Contract Public Private Partnership (PPP)
Technology Dissolved Air Filtration Flotation (DAFF) and Bacteriologically Activated Carbon (BAC)
Water Capacity 165 ML/d expandable to 240 ML/d
Facilities Water treatment plant, pumping station and integration works
Project Term 37 years
Capital Cost Less than $300M
Operations Commencement July 2013
* approximate


Project Overview

The Mundaring Water Treatment Plant will be the major source of water for around 33,000 rural and town services that comprise the Goldfields and Agricultural Water Supply Scheme.  This will be a critical asset designed to manage the challenge of treating water from three different sources.

The project, the Water Corporation’s first public private partnership (PPP), awarded to Helena Water in July 2011, with an October 2011 commencement date on site and a practical completion date for the second quarter of 2013.

As part of Helena Water, TRILITY welcomes the opportunity to partner with the Water Corporation to secure a safe and high quality water supply for regional Western Australia.

http://www.watercorporation.com.au/M/mundaring_wtp.cfm