TasWater Regional Towns Water Supply Program*
Client
TasWater
Type of contract
Design and Construction (D&C) and the subsequent operational support for a period of two years
Facilities
N/A
Technology
Ultrafiltration, granular activated carbon filtration, pH balancing and ultraviolet treatment
Design capacity
Township Capacity (kL/d)
Bronte Park 104
Conara 222
Cornwall 25
Gladstone 40
Herrick 24
Mathinna 50
Rossarden 49
Wayatinah 50
Term
Design, planning and construction – 62 weeks. Operational support ongoing until practical completion
Capital cost
N/A
Services
- Water treatment
Facilities
N/A
TasWater Regional Towns Water Supply Program*
TRILITY was selected by TasWater to design and construct Work Package One of the TasWater Regional Towns Water Supply Program. Work Package One is the design and construction of water treatment plants and the subsequent operational support for a period of one year for eight of sixteen townships around Tasmania.
One of those townships, Rossarden won the 2021 award for having the ‘Best Tasting Municipal Water in the World.’ Read more